Swing Bridge Construction Update: Week of May 25, 2025

Submitted by Sara Mendillo

(May 25, 2025) — The Connecticut Department of Transportation advises the following construction activities will take place at the Haddam/East Haddam Swing Bridge (Route 82) during the upcoming week of May 25, 2025:

Overnight Bridge Closures 

There are no overnight bridge closures scheduled for the upcoming week.

Daytime Lane Closures

  • Single lane closures on Route 82 occur Monday through Friday between 9:00 a.m. and 3:00 p.m. within the project limits. Traffic flaggers will coordinate the alternating traffic sequence.
  • Both lanes will be reopened and operational during peak traffic hours.

Marine Advisory

Boaters are advised that the bridge has returned to its normal USCG-required operating schedule. The bridge now opens on the hour (as needed) between 6:00 a.m. and 8:00 p.m. The bridge operator can be reached at 860-218-4973. Please be advised that this phone number is designated for marine use only. 

Mariners are advised that the contractor’s suspended scaffold has been removed from spans 3 and 4. The contractor still has scaffolding hung in span 2.

The tide clearance board is recommended as the best reference for gauging clearance at time of passage. The board is located on the bulkhead at Goodspeed, and has been set to indicate the vertical clearance to the contractor’s suspended scaffold.

Text Alerts

You can sign up for Text Alerts to receive notifications on bridge closures and re-openings, closure cancellations, and any emergency closures. To opt in, text the word SWINGBRIDGE to 888777. (Message and Data rates may apply). In addition to SMS messages, if you would like to receive Swing Bridge open/closed status notices via email or a voice call from Everbridge, please click here to enter the required information. Message and data rates may apply. Reply HELP for help, STOP to opt out.

Webcams

Project WEBCAMS for monitoring traffic conditions on the bridge (one on each side of the river) and tide board clearance for maritime information are available 24/7. The camera feeds are viewable from our project website homepage.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Hot this week

HVFC Responds to Fiery Crash That Closed Route 9

By Olivia Drake, HVFC Public Information Officer (March 24, 2024)...

Memorial Service Announced for Haddam Man Found in Cockaponset State Forest

By Edith Pawlicki (October 14, 2024) --- A celebration of...

Letter to the Editor: In Opposition to Sale of the Rossi Property

The views stated here are those of the authors...

Nathaniel B. Field Memorial Foundation Wins Grant from Eversource

Submitted by Marie and Howie Field (March 30, 2024) ---...

KCF Receives Grant to Fund College Scholarships for High School Seniors

Submitted by Kathleen Amoia (March 5, 2024) --- The Killingworth...

Programs and Events at Brainerd Memorial Library: July 2025

Submitted by Andrew Maloney, Executive Director, Brainerd Memorial Library (July...

Middlesex Chamber Seeks Nominees for Veterans Community Service Award

Submitted by Haley Stafford (July 7, 2025) --- The Middlesex...

Thomas Casey Joins Essex Savings Bank as Vice President

Submitted by Lucas Fumiatti, Essex Savings Bank (July 7, 2025)...

RiverCOG Hosts Household Hazardous Waste Collection July 19th

Submitted by Eliza LoPresti (July 7, 2025) --- The Lower...

Andrew Ferguson Completes Fire Service Class at Fire Academy

By Olivia Drake, HVFC Public Information Officer (July 7, 2025)...

A Notable Celebration for Haddam-Killingworth Mentoring Program

Submitted by Ray Galloway (July 6, 2025) ---- On May...
Advertisements

Related Articles

Advertisements
Advertisements
Advertisements