Thursday, November 21, 2024
HomeNewsHaddam Town GovernmentEast Haddam Swing Bridge Project Weekly Update: Construction Activities - Week of September...

East Haddam Swing Bridge Project Weekly Update: Construction Activities – Week of September 26, 2022

By Town of Haddam.

(September 28, 2022) —The Connecticut Department of Transportation advises the following construction activities for the upcoming week: 

Daytime:
Roadway
Crews will continue working on driveway realignment and staging for installation of a new retaining wall on the east side of Route 82 (Haddam side).

Bridge
Crews will be troubleshooting and repairing the recent mechanical breakdown of the swing span.

Nighttime:
No anticipated night activities.

Vehicle/Marine Impacts:
No anticipated lane closures this week.

Until  further notice, the bridge will not open to marine traffic due to the mechanical issues occurring with the swing span of the bridge.

Please be advised:
Weekend work is not anticipated.

Signs will be posted to help guide the public.

Access to local businesses and residents within the work zones will be maintained.

Unforeseen circumstances have the potential to impact all scheduled construction activities.

The Connecticut Department of Transportation is working to inform residents of current and upcoming construction activities through announcements such as this, as well as the project website. For more information, visit https://easthaddamswingbridgeproject.com/

If you have any questions related to construction, please send an e-mail to dotproject40-141@ct.gov

Must Read