Tylerville Roundabouts Project Two-Week Look-Ahead: September 3, 2024

Submitted by Sara Mendillo

(September 3, 2024) — The Connecticut Department of Transportation has provided the following two-week look-ahead for the Tylerville Roundabouts project in Haddam:

Northern Roundabout
Anticipate alternating one-way traffic along Route 154 during the overnight hours, as drainage and water main work resume.

Southern Roundabout
The Southern Roundabout will continue to be very active.  The biggest construction-related traffic impacts will be as follows:

1. Lane Shift of Route 154 occurred on August 31, 2024.

  • The contractor re-striped the intersection of Route 154 to accommodate the new traffic barrier pattern. Concrete barrier was shifted on September, 3, 2024 to match the newly painted lines. This will be the new configuration for the near future.

    2. Contractor plans to start full depth reconstruction at the southern limits of the south roundabout.

  • Contractor will be excavating out the existing pavement and will be back-filling with processed aggregate. During this activity, the traveling public will be traveling along process aggregate, compacted gravel material, for the time being.
  • During this time, the contractor will have cones and lane divider signs running along Route 154 to delineate where the traffic needs to go.

*Please note the contractor is allowed ten calendar days for the traveling public to ride along process aggregate before it needs to be paved. The public should use caution and should expect the pavement to be removed starting Monday, September 9, 2024.*

3. The remaining traffic impacts will be truck traffic entering and exiting the site for material and equipment deliveries.

Please note the contractor is not allowed to impact traffic within the following time frames (within shifting stages):

Monday through Friday: 6:00 a.m. to 9:00 a.m. and 3:00 p.m. to 6:00 p.m.
Saturday and Sunday: 10:00 a.m. to 6:00 p.m.

All traffic patterns and/or project work are subject to change as necessary.  Construction of this nature requires flexibility, as it requires the coordination of many sub-contractors and sequenced work.

Hot this week

HVFC Responds to Fiery Crash That Closed Route 9

By Olivia Drake, HVFC Public Information Officer (March 24, 2024)...

Nathaniel B. Field Memorial Foundation Wins Grant from Eversource

Submitted by Marie and Howie Field (March 30, 2024) ---...

Letter to the Editor: In Opposition to Sale of the Rossi Property

The views stated here are those of the authors...

KCF Receives Grant to Fund College Scholarships for High School Seniors

Submitted by Kathleen Amoia (March 5, 2024) --- The Killingworth...

Memorial Service Announced for Haddam Man Found in Cockaponset State Forest

By Edith Pawlicki (October 14, 2024) --- A celebration of...

The 1965 Windsor Locks Little League World Series Championship Team

(August 24, 2024) — To baseball fans across the...

CANCELLED: Waberi Jordan Concert at The Buttonwood Tree

Submitted by The Buttonwood Tree (December 19, 2024) --- The...

Higganum Author Publishes Young Adult Novel

Submitted by Gary Feinstein (October 17, 2024) --- Local author...

Brainerd Memorial Library to Close for Two Weeks

Submitted by Robbie Marshall, Brainerd Memorial Library (October 17, 2024)...

Programs/Events at Spectrum Gallery, October/November/December 2024

Submitted by Barbara Nair, Spectrum Gallery (October 17, 2024) ---...

Legislative Candidate Announces Endorsements

Submitted by Renee LaMark Muir (October 17, 2024) --- Renee...

Haddam/Killingworth Community Calendar: October 17 – 24, 2024

Haddam-Killingworth Town & Community Calendar Please visit www.haddam.org, www.townofkillingworth.com, www.hk-now.com,...
spot_img

Related Articles

Popular Categories

spot_imgspot_img