Tylerville Roundabouts Project: Two-Week Lookahead, August 19, 2024

Submitted by Sara Mendillo

(August 19, 2024) — The Connecticut Department of Transportation has provided the following two-week lookahead for the Tylerville Roundabouts project in Haddam:

Northern Roundabout
No work is expected on the Northern Roundabout over the next couple of weeks.  The contractor, Richards, has allocated all of its manpower to the day shift for the upcoming Bridge Install.  Nightwork/Drainage will resume during the first weeks of September.

Southern Roundabout
The Southern Roundabout will continue to be very active.  Most of the work here will still occur off the roadway behind the barrier and pertain to the bridge construction.  The current orientation continues as the staging for the foreseeable future.  There will be slight lane adjustments on Route 154 going both north and south at the intersection with the Route 82 Connector.  The contractor will be placing concrete barriers and removing the existing guiderail to accommodate these lane shifts.  The biggest construction related traffic impacts will be as follows:

  • Truck traffic entering and exiting the site.
  • The Pre-Cast Concrete bridge is scheduled to be set on Tuesday August 27, 2024 (tentative date).  This work will include delivery of the thirteen excessively large pre-cast concrete pieces, and the unloading and setting of each piece. Richards will be utilizing a crane while setting the pieces, which may require stoppage of traffic.  NOTE: The contractor is allowed ten minutes of full vehicle stoppage at a time.
  • Material/Equipment Deliveries.
NOTE: The contractor is not permitted to impact traffic within the following time frames (within shifting stages):

Monday through Friday: 6:00 a.m. to 9:00 a.m. and 3:00 p.m. to 6:00 p.m.

Saturday and Sunday: 10:00 a.m. to 6:00 p.m.
All traffic patterns and/or project work are subject to change as necessary.  Construction of this nature requires flexibility, as it requires the coordination of many sub-contractors and sequenced work.

Hot this week

Eversource Files for Lower Standard Service Supply Rate

Submitted by Sarah Paduano, Eversource Energy (May 19, 2025) ---...

New in Killingworth: From “Cooking Company” to “AristoKraft Kitchen”

By Clark Judge (February 4, 2026) --- In the spring...

HVFC Responds to Fiery Crash That Closed Route 9

By Olivia Drake, HVFC Public Information Officer (March 24, 2024)...

Memorial Service Announced for Haddam Man Found in Cockaponset State Forest

By Edith Pawlicki (October 14, 2024) --- A celebration of...

Letter to the Editor: In Opposition to Sale of the Rossi Property

The views stated here are those of the authors...

Veterans Helping Veterans: Saving the Higganum/Haddam VFW

By Janice Sina (March 5, 2026) --- Think about March...

Art Classes and Workshops Offered by Spectrum Gallery

Submitted by Barbara Nair (March 5, 2026) --- The following...

Haddam/Killingworth Community Calendar March 5 – 12, 2026

Haddam/Killingworth Town and Community Calendar Please visit www.haddam.org, www.townofkillingworth.com, www.hk-now.com,...

Former Haddam Town Clerk Files Complaint with CHRO

The following item was reported by Marc E. Fitch...

Artists Wanted for Essex Town Green Summer Arts Festival

Submitted by Barbara Nair (March 4, 2026) --- Arts Center...

Programs and Events at Essex Library, March 2026

Submitted by Elizabeth Reinhart (March 4, 2026) --- The following...

Deer Lake Trail Run Returns to Killingworth April 26th

By Jenn Carroll (March 4, 2026) --- Deer Lake Outdoor...

Higganum Farmers Market Returns to Brainerd Library in May

Submitted by Robbie Marshall (March 3, 2026) --- Brainerd Memorial...

Related Articles