Swing Bridge Update: Week of June 2, 2024

Submitted by Sara Mendillo

(June 2, 2024) — The Connecticut Department of Transportation advises the following construction activities at the Haddam/East Haddam Swing Bridge (Route 82) for the upcoming week of June 2, 2024:

63-Hour Bridge Closure
There will be a 63-hour bridge closure this week. Closure begins Sunday, June 2, 2024 at 8:00 p.m. The bridge reopen on Wednesday, June 5, 2024 at 11:00 a.m.

Overnight Bridge Closures

In addition to this week’s 63-hour closure, there will be overnight bridge closures on Wednesday, Thursday and Friday as follows:

  • Wednesday night (6/5) into Thursday morning (6/6) – 11:00 p.m. to 6:00 a.m.
  • Thursday night (6/6) into Friday morning (6/7) – 11:00 p.m. to 6:00 a.m.
  • Friday night (6/7) into Saturday morning (6/8) – 11:30 p.m. to 8:00 a.m.

 

  • Marine Advisory

    Boaters are advised that the Swing Bridge opening schedule for 6/2/24 through 6/8/24 will be as follows:

    • Sunday at 5:00 p.m.
    • Monday NO Openings.
    • Tuesday NO Openings.
    • Wednesday NO Openings.
    • Thursday at 10:00 a.m. and 2:00 p.m.
    • Friday at 10:00 a.m., 2:00 p.m. and 5:00 p.m.
    • Saturday at 10:00 a.m., 2:00 p.m. and 5:00 p.m.

    Inclement weather and other unforeseen circumstances could impact the dates of 63-hour closures. A mariner notice will be issued at least 24-hours prior to the start of a cancellation.

    Be advised that the contractor is still working through the testing stages of the new mechanicals on the swing span, so potential delays or openings being cancelled could occur if technical issues arise during a swing attempt.

    Additionally, on days when wind gusts are 25 mph or higher, swing span openings will be cancelled. Mariners intending to pass through the bridge are encouraged to monitor the wind forecast on their navigation day and call the bridge operator.

    Be advised that in the location where the contractor has removed scaffolding, there is approximately three feet of additional clearance.

    The Tide Clearance Board is recommended as the best reference for gauging clearance at time of passage. The Board is located on the bulkhead at Goodspeed, and has been adjusted to reflect the vertical clearance to the contractor’s suspended scaffold. The tide board WEBCAM for monitoring the clearance can be viewed 24/7 from our project website homepage on Camera 3.

    The bridge operator can be reached at 860-218-4973.

  • Text Alerts
    • You can sign up for Text Alerts to receive notifications on bridge closures and re-openings, closure cancellations, and any emergency closures. To opt in, text the word SWINGBRIDGE to 888777. (Message and Data rates may apply). In addition to SMS messages, if you would like to receive Swing Bridge open/closed status notices via email or a voice call from Everbridge, please click here to enter the required information. Message and data rates may apply. Reply HELP for help, STOP to opt out.

Hot this week

Eversource Files for Lower Standard Service Supply Rate

Submitted by Sarah Paduano, Eversource Energy (May 19, 2025) ---...

New in Killingworth: From “Cooking Company” to “AristoKraft Kitchen”

By Clark Judge (February 4, 2026) --- In the spring...

A Tribute to Tom Grasso (1973-2026) Heroic Soldier, Teacher and Coach

By Phil Devlin (May 12, 2026) --- On June 10,...

HVFC Responds to Fiery Crash That Closed Route 9

By Olivia Drake, HVFC Public Information Officer (March 24, 2024)...

Memorial Service Announced for Haddam Man Found in Cockaponset State Forest

By Edith Pawlicki (October 14, 2024) --- A celebration of...

RSD 17 Education Budget Referendum Today (July 15, 2026)

By Editorial Staff (July 15, 2026) --- The referendum for...

Haagas’ Last EMT Class Set for August in Killingworth

By Clark Judge   (July 15, 2026) --- Mike and Marguerite...

Haddam Business Receives Grant from Middlesex County Revitalization Commission

Submitted by Haley Stafford, Middlesex County Chamber of Commerce   (July...

U.S. Coast Guard Band Returns to Parmelee Farm July 26th

Submitted by Doreen Staskelunas, Haddam Senior Center Activities Coordinator (July...

Higganum Students Earn Dean’s List Honors at Salve Regina University

Merit Pages News (July 14, 2026) --- The following students...

Eversource Customers Helped Reduce Peak Demand During Early July Heat Wave

Submitted by Tricia Modifica, Eversource   (July 14, 2026) --- When...

Notice to Haddam Voters: Democratic Party Primary August 11th

Submitted by Haddam Registrars of Voters (July 14, 2026) --- ...
Advertisements

Related Articles

Advertisements
Advertisements
Advertisements