(December 17, 2023) — The Connecticut Department of Transportation advises the following construction activities at the Haddam/East Haddam Swing Bridge for the upcoming week of December 17, 2023. There will be complete overnight closures as follows:

  • Sunday night (12/17) into Monday morning (12/18) – 10:00 p.m. to 6:00 a.m.
  • Monday night (12/18) into Tuesday morning (12/19) – 7:00 p.m. to 6:00 a.m.
  • Tuesday night (12/19) into Wednesday morning (12/20) – 7:00 p.m. to 6:00 a.m.
  • Wednesday night (12/20) into Thursday morning (12/21) – 11:00 p.m. to 6:00 a.m.
  • Thursday night (12/21) into Friday morning (12/22) – 11:00 p.m. to 6:00 a.m.
  • Marine Advisory
  • The swing span is no longer opening to accommodate marine traffic passage, scheduled openings will resume on April 1, 2024.
  • Text Alerts
  • You can sign up for text alerts to receive notifications on bridge closures and re-openings, closure cancellations, and any emergency closures. To opt in, text the word SWINGBRIDGE to 888777. (Message and Data rates may apply). In addition to SMS messages, if you would like to receive Swing Bridge open/closed status notices via email or a voice call from Everbridge, please click here to enter the required information. Message and data rates may apply. Reply HELP for help, STOP to opt out.